Bitdeer | Sparks U.S. Manufacturing Facility

Bitdeer announced that it had broken ground in Sparks, Nevada for its first U.S. manufacturing and assembly facility; capacity and completion timing remain company expectations.

Activity / Release Date
2026/07/09
Data Card Published
2026/08/31
Last verified
2026/08/31
Current status
AnnouncedReview After the Expected Completion Date
What Happened

What happened

On July 9, Bitdeer said it had broken ground in Sparks for a 187,000-square-foot electronics manufacturing facility, with investment covering the plant, equipment and construction.

Verified Facts

Confirmed facts

These fields contain only information directly supported by sources. Manufacturer claims and unrealized expectations are labeled separately.

Confirmed progress
Groundbreaking completed in Sparks, Nevada
source 01
Announced investment and size
USD 36 million | 187,000 square feet
source 01
Facility role
Bitdeer's first U.S. manufacturing and assembly footprint
source 01
Manufacturer-expected completion
By the end of 2026
Company expectation; not yet an achieved resultsource 01
Manufacturer expects
10,000 SEALMINER units per month; 70 jobs
Company expectation; not yet an achieved resultsource 01
Miner Impact

What does it mean for miners?

A domestic manufacturing footprint may eventually affect the North American supply chain, but it does not yet establish improved miner prices, tariff treatment, delivery times or available quantities.

JGM Learn Analysis

Analysis of this site

Groundbreaking is a reported completed action. End-2026 completion, 10,000 units per month and 70 jobs are company expectations and should be presented as projections, not current capacity.

This section is JGM Learn's neutral interpretation of the listed sources. It is not manufacturer copy and does not guarantee returns, delivery or investment outcomes.
Primary Sources

Sources and Verification Record

Sources prioritize manufacturer websites, investor-relations releases and first-party event records. A source date is not necessarily the event date.

  1. 01
    Bitdeer to Open $36 Million Advanced Tech Manufacturing Facility in Sparks, Bringing 70 High-Tech Jobs to NevadaGo to original source ↗

    Bitdeer Technologies Group · Investor Relations Announcement · 2026/07/09

    View: 2026/08/31
Update Record

Update and Correction Record

  1. Created the data card and completed the initial source review.
Cite this page

Copy the Chinese citation, English citation or permanent URL.

  • The confirmed facts on this page are compiled from the listed original sources.
  • JGM Learn analysis is original editorial analysis by this site.
  • Manufacturer logos, product images and third-party visuals are not covered by this site's text and data citation permission.